an industry best practice and expectation in doe order 413 3b ipmr and clause doe h 2024 the sra identifies the high risk areas of the project schedule determines the ...

icon picture PPTX Filetype Power Point PPTX | Posted on 02 Sep 2022 | 3 years ago
Partial capture of text on file.
                                       An industry best practice and expectation 
                                        in DOE Order 413.3B, IPMR, and Clause 
                                        DOE-H-2024, the SRA:
                                            Identifies the high-risk areas of the 
                                             project;
           Schedule                         Determines the likelihood of risk 
                                             materializing; 
                      Risk                  Assesses the impact of possible risk.
       Assessmen                       Conducted by the Contractor, the Initial 
                                        SRA assessment should begin as soon as 
                               t        the project baseline is implemented.
                                       The SRA uses Statistical techniques in the 
                                        form of Monte Carlo simulations to 
                                        quantify the impact of duration 
                                        uncertainties, and technical, 
                                        programmatic, and schedule risk on the 
                                        project’s schedule.                             2
         Traditional Scheduling
         In a project’s Integrated Master Schedule, there are single 
          dates chosen for the start and finish for each activity.
         This is called a “Deterministic” approach.
                                         15-Days of 
                                          Duration
                                          Activity A
                              May 1                     May 
                                                        15
                    Project Duration, however, has 
                                  Uncertainty                                         3
         Probabilistic Scheduling
         Approaches duration estimates with uncertainty; Forms a 
         Distribution    Curve for each activity
                                         Most 
                                        Likely 
                                       Duration
                            Best Case                           Worst Case
                            (optimisti                          (pessimistic)
                            c)
                                   25     35                   90
                        Activities are assigned a duration uncertainty range
                   Durations are not “random” but assigned a 3-point estimated 
                                              duration
          Critical, Near Critical, and High-Risk activities should have a 
            range determined by the Control Account Manager
          Remainder of activities can have ranges determined globally: 
                                                                                        4
            Banding
       SRA Process and Results
                                                                  5
       SRA Process and Results
                                                                  6
The words contained in this file might help you see if this file matches what you are looking for:

...An industry best practice and expectation in doe order b ipmr clause h the sra identifies high risk areas of project schedule determines likelihood materializing assesses impact possible assessmen conducted by contractor initial assessment should begin as soon t baseline is implemented uses statistical techniques form monte carlo simulations to quantify duration uncertainties technical programmatic on s traditional scheduling a integrated master there are single dates chosen for start finish each activity this called deterministic approach days may however has uncertainty probabilistic approaches estimates with forms distribution curve most likely case worst optimisti pessimistic c activities assigned range durations not random but point estimated critical near have determined control account manager remainder can ranges globally banding process results...

no reviews yet
Please Login to review.