sheet 1 instructions instructions for dt1923 contract time for completion spreadsheet see fdm 191030 for general information on the contract time for completion analysis 1 the form is locked information ...

icon picture XLSX Filetype Excel XLSX | Posted on 14 Aug 2022 | 3 years ago
Partial file snippet.
Sheet 1: Instructions
Instructions for DT1923 - Contract Time for Completion Spreadsheet

See FDM 19-10-30 for general information on the Contract Time for Completion analysis.

1. The form is locked. Information can only be entered in the yellow shaded cells.
2. Enter project information at the top of the form.
3. Enter the construction year at the bottom of the page to automatically fill out all the Begin and End dates for each month. Then, delete Begin and End dates for months before the anticipated start date, and after the anticipated completion date. Change the Begin date for the applicable month to the actual probable date of beginning and change the end date for the applicable month to the anticipated completion date. Under the Month column, delete names for unused months to remove the labels from the Gantt Chart.
4. Check the box for the Contract Work Type to be used.
5. Enter number of holiday days for each month. See FDM 19-15-23 for how to enter for Independence Day.
6. If work is expected to take place on weekends or holidays during a month, fill in the number of these days under Adjusted Work Days Modifier. This will adjust the total possible work days before applying the probable work day percentage.
7. Enter probable working day percentage based on the work type (see FDM 19-10 Attachment 30.2).
8. Totals for Calendar Days Contract and Working Day Contract are autofilled based on the calculated totals from the bottom left table. These can be overwritten if necessary. Round to 5 day increments. Fill in the anticipated completion date if the contract will be a Completion Date Contract.
9. Enter controlling items on left side of page under Item Analysis.
10. Enter item quantities for each stage (all stages do not need to be used).
11. Enter item units and production rates (also see FDM 19-10-30.3).
12. Enter begin day for each item and stage (the end date will be calculated automatically). Tip: You can use a formula here, for instance to start Item 2 when Item 1 is done, you would enter =W30 in cell V31. That way if you add 2 days to Item 1, the start date for Item 2 will automatically adjust by 2 days.
13. If the default "Stage 1", "Stage 2", etc., doesn't work for your project, you can edit them in the yellow shaded cells. The legend and other column headings will update automatically.
14. Enter remarks as necessary to provide work restrictions, interim completions, etc.
15. To get rid of extra days (blank space) on the right side of the Gantt Chart, right click on the top axis and select "Format Axis". Under "Axis Options", Change "Maximum" from "Auto" to "Fixed" and set the value to the total number of working days for the contract.
16. Create a separate Time Chart sheet for each calendar year of construction if there are multiple years. Put the overall working days, calendar days, or completion date on each sheet.


Contact Rielly O'Donnell (rielly.odonnell@dot.wi.gov) with any suggested revisions to this form.

Sheet 2: Blank Time Chart
CONTRACT TIME FOR COMPLETION

Wisconsin Department of Transportation DT1923 04/2021

































Project ID 5215-00-67
Highway STH 35

Project Title Lancaster - Bloomington



Date of Letting March 8, 2022

Work Type Resurfacing
County Grant

Project Limits McKinley St to Grant River Bridge



Probable Date of Beginning June 1, 2022
















































ITEM ANALYSIS

Item Contract Quantity per Stage Total Quantity Unit Production Rate Working Days
(per Stage)
Milling Overlay Finishing



Milling Overlay Finishing - - Begin End Begin End Begin End Begin End Begin End

1. Traffic Control 40



40 Days 1 40 /
/
/
/
0 40








2. Pipe Underdrain 63



63 LF 60 2 /
/
/
/
1 2









3. Milling 125,655



120,000 SY 10000 13 /
/
/
/
3 16









4. HMA Pavement Overlay
14,800


14,800 Tons 1,000
/ 15 /
/
/


6 21







5. Base Aggregate Dense 3/4 Inch
2,200


2,200 Tons 300
/ 8 /
/
/


21 29







6. Rumble Strip Centerline

25,204

25,204 LF 8,450
/
/ 3 /
/




29 32





7. Pavement Marking

110,000

110,000 LF 36,000
/
/ 4 /
/




32 36





8. Finishing Roadway

4

4 Days 1
/
/ 4 /
/




36 40















/
/
/
/






















/
/
/
/






















/
/
/
/






















/
/
/
/






















/
/
/
/






















/
/
/
/






















/
/
/
/






















/
/
/
/






















/
/
/
/






















/
/
/
/






















/
/
/
/






















/
/
/
/













































Date Days
Possible Work Days Additional Work Days Modifier Adjusted Possible Work Days Probable Work Days

Note: Chart is based on the assumption of work not occuring on weekends or holidays. If work is expected to occur on these days, adjust Possible Work Days by adding days to the Additional Work Days Modifier column. See FDM 19-10-30.

Month Begin End Month Total Holiday % Month Total






0 0
0
0
0 0

REMARKS













0 0
0
0
0 0

Rates determined using WisDOT production rate table. Lower rates used based on flagging operations. STH 35 will be open to two-way traffic at all times except through the work zone that utilizes traffic control for lane closures with flagging operations.




0 0
0
0
0 0






0 0
0
0
0 0






0 0
0
0
0 0



June 6/1/2022 6/30/2022 30 30 0 23
23 80 18 18



July 7/1/2022 7/31/2022 31 61 1 21
21 85 18 36



August 8/1/2022 8/5/2022 5 66 0 5
5 85 4 40






0 66
0
0
0 40

Contract Work Type










0 66
0
0
0 40




66








0 66
0
0
0 40


Working Day

40
Prepared By




0 66
0
0
0 40


Completion Date

August 5, 2022
Erin Clements









































Page 1 of 1 CONSTRUCTION YEAR: 2022












The words contained in this file might help you see if this file matches what you are looking for:

...Sheet instructions for dt contract time completion spreadsheet see fdm general information on the analysis form is locked can only be entered in yellow shaded cells enter project at top of construction year bottom page to automatically fill out all begin and end dates each month then delete months before anticipated start date after change applicable actual probable beginning under column names unused remove labels from gantt chart check box work type used number holiday days how independence day if expected take place weekends or holidays during a these adjusted modifier this will adjust total possible applying percentage working based attachment totals calendar are autofilled calculated left table overwritten necessary round increments controlling items side item quantities stage stages do not need units production rates also tip you use formula here instance when done would w cell v that way add by default quot etc doesn t your edit them legend other headings update remarks as provi...

no reviews yet
Please Login to review.