RENCANA ANGGARAN BIAYA (RAB) |
UNIT KERJA |
: DINAS KELAUTAN DAN PERIKANAN KABUPATEN KOTABARU |
|
|
|
|
|
KEGIATAN |
: PENGEMBANGAN, PENGELOLAAN SARANA DAN PRASARANA PANGKALAN PPENDARATAN IKAN |
|
|
|
|
|
|
|
|
( DANA DAK DAN PENDAMPING ) |
|
|
|
|
|
PEKERJAAN |
: PEMBUATAN INSTALASI PENGOLAHAN AIR LIMBAH DI LOKASI PENGEMBANGAN KAWASAN PPI |
|
|
|
|
|
LOKASI |
: PPI SAIJAAN - KABUPATEN KOTABARU |
|
|
|
|
|
|
|
|
|
|
|
|
No. |
URAIAN PEKERJAAN |
PERHITUNGAN |
VOLUME |
VOLUME KONTRAK |
1 |
2 |
3 |
4 |
5 |
|
|
|
|
|
I. |
Pekerjaan Persiapan |
|
|
|
|
|
|
|
1 |
Pembersihan Lokasi |
1.00 |
1.00 |
1.00 |
Ls |
|
|
|
|
|
|
|
|
|
II. |
Pekerjaan Tanah |
|
|
|
|
|
|
|
1 |
Galian tanah pondasi |
Bak IPAL (7 +8) /2 X (4+5) /2 X 1,50 |
50.63 |
70.00 |
M3 |
|
|
|
|
|
Pipa Inlet 17 X 0,4 X 0,5 |
3.40 |
|
|
|
|
|
|
|
Pipa Penguras 5 X 0,4 X 1,5 |
3.00 |
|
|
|
|
|
|
|
Saluran Pasangan Bata 131,75 X 0,6 X 0,5 |
86.23 |
|
|
|
|
|
|
|
|
143.25 |
|
|
|
|
|
|
|
|
|
|
|
2 |
Urugan tanah kembali |
40% X(7 +8) /2 X (4+5) /2 X 1,50 |
57.30 |
38.50 |
M3 |
3 |
Urugan pasir bawai lantai kerja 5 cm |
7 X 4 X 0,05 |
1.40 |
1.40 |
M3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
III. |
Pekerjaan Pasangan dan Beton |
|
|
|
|
|
|
|
1 |
Cor beton lantai kerja K - 100 = 5 cm |
7 X 4 X 0,05 |
1.40 |
1.40 |
M3 |
2 |
Pancangan kayu bulat dia. 10-12 cm, |
5 X 9 |
45.00 |
45.00 |
Btg |
|
pj. 2 meter bawah lantai, jarak 75 cm |
|
|
|
|
3 |
Beton bertulang K-225 : |
|
|
|
|
|
a. Lantai beton 15 cm |
7 X 4 X 0,15 |
4.20 |
4.20 |
M3 |
|
b. Lantai beton 15 cm |
6,2 X 3,2 X 0,15 |
2.98 |
|
M3 |
|
c. Kolom beton 20X20 cm |
8 X 2 X 0,20 X 0,20 |
0.64 |
0.64 |
M3 |
|
|
|
|
|
|
|
|
|
|
d. Balok Beton 20X20 cm |
5 X 3,2 X 0,20 X 0,20 |
0.64 |
1.23 |
M3 |
|
|
|
|
|
12,4 X 0,20 X 0,20 |
0.50 |
|
|
|
|
|
|
|
|
1.14 |
|
|
4 |
Pasangan Batu Bata 1 : 2, 1 Bata |
(6 X 1,80 X 1,8) + (2 X 2,80 X1,80) + (2 X 2,80 X 1,25) |
36.52 |
49.05 |
M2 |
5 |
Plesteran 1 : 4, t = 15 mm |
2 X (6 X 1,80 X 1,8) + (2 X 2,80 X1,80) + (2 X 2,80 X 1,25) |
73.04 |
124.64 |
M2 |
6 |
Acian dinding luar |
2 X (6 X 1,80 X 1,8) + (2 X 2,80 X1,80) + (2 X 2,80 X 1,25)+(6,20x3,20) |
92.88 |
94.76 |
M2 |
|
|
|
|
|
|
|
|
|
IV. |
Pekerjaan Lain-lain |
|
|
|
|
|
|
|
1 |
Waterproofing dinding dalam |
(6 X 1,80 X 1,8) + (2 X 2,80 X1,80) + (2 X 2,80 X 1,25) |
36.52 |
57.80 |
M2 |
2 |
Pipa Inlet SNI dia. 8" |
2+11+5+21+21+6 |
66.00 |
2.00 |
M' |
3 |
Pipa Outlet SNI dia. 8" |
2.00 |
2.00 |
2.00 |
M' |
4 |
Pipa Penguras SNI dia. 4" |
8.00 |
8.00 |
8.00 |
M' |
5 |
Stop Kran 4" |
1.00 |
1.00 |
1.00 |
Bh |
6 |
Saluran air pasangan bata |
27+21+41+18+13+11,75 |
131.75 |
600.00 |
M' |
|
|
|
|
|
|
|
|
|
ANALISA HARGA SATUAN PEKERJAAN SNI 2007 |
|
|
|
|
|
|
|
|
1 |
Menggali 1 m3 tanah biasa sedalam 1 meter |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Tenaga Kerja |
Pekerja |
OH |
0.750 |
94,200.00 |
70,650.00 |
|
Mandor |
OH |
0.025 |
112,100.00 |
2,802.50 |
|
Jumlah harga per-satuan pekerjaan |
73,452.50 |
|
|
|
|
|
|
|
|
2 |
Menggali 1 m3 tanah biasa sedalam 2 meter |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Tenaga Kerja |
Pekerja |
OH |
0.900 |
94,200.00 |
84,780.00 |
|
Mandor |
OH |
0.045 |
112,100.00 |
5,044.50 |
|
Jumlah harga per-satuan pekerjaan |
89,824.50 |
|
|
|
|
|
|
|
|
3 |
Mengurug kembali 1 m3 galian |
|
|
|
|
|
|
|
Mengurug kembali 1 m3 galian dihitung dari 1/3 dari indeks pekerjaan galian |
|
|
|
|
|
|
|
|
|
|
|
0.333 |
73,452.50 |
24,459.68 |
|
|
|
|
|
|
|
|
4 |
Mengurug 1 m3 psir urug |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Pasir Urug |
M3 |
1.200 |
142,700.00 |
171,240.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.900 |
94,200.00 |
84,780.00 |
|
Mandor |
OH |
0.045 |
112,100.00 |
5,044.50 |
|
Jumlah harga per-satuan pekerjaan |
261,064.50 |
|
|
|
|
|
|
|
|
5 |
Mengurug 1 m3 tanah urug untuk peninggian bangunan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Pasir Urug |
M3 |
1.200 |
142,700.00 |
171,240.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.250 |
94,200.00 |
23,550.00 |
|
Mandor |
OH |
0.025 |
112,100.00 |
2,802.50 |
|
Jumlah harga per-satuan pekerjaan |
197,592.50 |
|
|
|
|
|
|
|
|
6 |
Memadatkan 1 m3 tanah (per 20 cm) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Tenaga Kerja |
Pekerja |
OH |
0.500 |
94,200.00 |
47,100.00 |
|
Mandor |
OH |
0.050 |
112,100.00 |
5,605.00 |
|
Jumlah harga per-satuan pekerjaan |
52,705.00 |
|
|
|
|
|
|
|
|
7 |
Mengurug 1 m3 tanah urug dipadatkan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Jumlah (Rp.) |
|
a. Mengurug 1 m3 tanah urug untuk peninggian bangunan |
197,592.50 |
|
b. Memadatkan 1 m3 tanah (per 20 cm) |
52,705.00 |
|
Jumlah harga per-satuan pekerjaan |
250,297.50 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8 |
Memasang 1 m3 pondasi batu, campuran 1 PC : 4 PP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Batu pondasi 15cm/20cm |
m3 |
1.200 |
183,600.000 |
220,320.00 |
|
Semen portland |
kg |
163.000 |
1,682.000 |
274,166.00 |
|
Pasir Pasang |
m3 |
0.520 |
149,300.000 |
77,636.00 |
|
Tenaga Kerja |
Pekerja |
OH |
1.500 |
94,200.000 |
141,300.00 |
|
Tukang Batu |
OH |
0.600 |
94,200.000 |
56,520.00 |
|
Kepala Tukang |
OH |
0.060 |
112,100.000 |
6,726.00 |
|
Mandor |
OH |
0.075 |
112,100.000 |
8,407.50 |
|
Jumlah harga per-satuan pekerjaan |
785,075.50 |
|
|
|
|
|
|
|
|
9 |
Membuat 1 m3 beton mutu K-100 (beton bawah lantai) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Semen portland |
kg |
247.000 |
1,682.000 |
415,454.00 |
|
Pasir Pasang |
m3 |
0.621 |
149,300.000 |
92,715.30 |
|
Kerikil (maks. 30mm) |
m3 |
0.740 |
221,200.000 |
163,688.00 |
|
Air |
liter |
215.000 |
200.000 |
43,000.00 |
|
Tenaga Kerja |
Pekerja |
OH |
1.650 |
94,200.000 |
155,430.00 |
|
Tukang Batu |
OH |
0.275 |
94,200.000 |
25,905.00 |
|
Kepala Tukang |
OH |
0.028 |
112,100.000 |
3,138.80 |
|
Mandor |
OH |
0.083 |
112,100.000 |
9,304.30 |
|
Jumlah harga per-satuan pekerjaan |
908,635.40 |
|
|
|
|
|
|
|
|
10 |
Membuat 1 m3 beton mutu K-150 (beton keliling bangunan) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Semen portland |
kg |
299.000 |
1,682.000 |
502,918.00 |
|
Pasir Pasang |
m3 |
0.571 |
149,300.000 |
85,250.30 |
|
Kerikil (maks. 30mm) |
m3 |
0.753 |
221,200.000 |
166,563.60 |
|
Air |
liter |
215.000 |
200.000 |
43,000.00 |
|
Tenaga Kerja |
Pekerja |
OH |
1.650 |
94,200.000 |
155,430.00 |
|
Tukang Batu |
OH |
0.275 |
94,200.000 |
25,905.00 |
|
Kepala Tukang |
OH |
0.028 |
112,100.000 |
3,138.80 |
|
Mandor |
OH |
0.083 |
112,100.000 |
9,304.30 |
|
Jumlah harga per-satuan pekerjaan |
991,510.00 |
|
|
|
|
|
|
|
|
11 |
Membuat 1 m' kolom praktis beton bertulang |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Kayu Kelas III |
m3 |
0.002 |
3,731,000.000 |
7,462.00 |
|
Paku 5cm - 12 cm |
kg |
0.010 |
18,800.000 |
188.00 |
|
Besi beton polos |
kg |
3.130 |
14,235.000 |
44,555.55 |
|
Kawat beton |
kg |
0.047 |
32,100.000 |
1,508.70 |
|
Semen Portland |
kg |
4.000 |
1,682.000 |
6,728.00 |
|
Pasir Pasang |
m3 |
0.006 |
149,300.000 |
895.80 |
|
Kerikil |
m3 |
0.009 |
221,200.000 |
1,990.80 |
|
Tenaga Kerja |
Pekerja |
OH |
0.180 |
94,200.000 |
16,956.00 |
|
Tukang Batu |
OH |
0.020 |
94,200.000 |
1,884.00 |
|
Tukang Kayu |
OH |
0.020 |
94,200.000 |
1,884.00 |
|
Tukang Besi |
OH |
0.020 |
94,200.000 |
1,884.00 |
|
Kepala Tukang |
OH |
0.006 |
112,100.000 |
672.60 |
|
Mandor |
OH |
0.009 |
112,100.000 |
1,008.90 |
|
Jumlah harga per-satuan pekerjaan |
87,618.35 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12 |
Membuat 1 m' ring balok beton bertulang |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Kayu Kelas III |
m3 |
0.003 |
22,100.000 |
66.30 |
|
Paku 5cm - 12 cm |
kg |
0.020 |
18,800.000 |
376.00 |
|
Besi beton polos |
kg |
3.130 |
14,235.000 |
44,555.55 |
|
Kawat beton |
kg |
0.047 |
32,100.000 |
1,508.70 |
|
Semen Portland |
kg |
5.500 |
1,682.000 |
9,251.00 |
|
Pasir Pasang |
m3 |
0.009 |
149,300.000 |
1,343.70 |
|
Kerikil |
m3 |
0.015 |
221,200.000 |
3,318.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.297 |
94,200.000 |
27,977.40 |
|
Tukang Batu |
OH |
0.033 |
94,200.000 |
3,108.60 |
|
Tukang Kayu |
OH |
0.033 |
94,200.000 |
3,108.60 |
|
Tukang Besi |
OH |
0.033 |
94,200.000 |
3,108.60 |
|
Kepala Tukang |
OH |
0.010 |
112,100.000 |
1,121.00 |
|
Mandor |
OH |
0.015 |
112,100.000 |
1,681.50 |
|
Jumlah harga per-satuan pekerjaan |
100,524.95 |
|
|
|
|
|
|
|
|
13 |
Membuat 1 m3 beton mutu K-225, slump (12 ± 2) cm, w/c = 0.58 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Semen portland |
kg |
371.000 |
1,682.000 |
624,022.00 |
|
Pasir Pasang |
m3 |
0.499 |
149,300.000 |
74,500.70 |
|
Kerikil (maks. 30mm) |
m3 |
0.776 |
221,200.000 |
171,651.20 |
|
Air |
liter |
215.000 |
200.000 |
43,000.00 |
|
Tenaga Kerja |
Pekerja |
OH |
1.650 |
94,200.000 |
155,430.00 |
|
Tukang Batu |
OH |
0.275 |
94,200.000 |
25,905.00 |
|
Kepala Tukang |
OH |
0.028 |
112,100.000 |
3,138.80 |
|
Mandor |
OH |
0.083 |
112,100.000 |
9,304.30 |
|
Jumlah harga per-satuan pekerjaan |
1,106,952.00 |
|
|
|
|
|
|
|
|
14 |
Pembesian 10 kg dengan besi polos atau besi ulir |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Besi beton (polos/ulir) |
kg |
10.500 |
14,235.000 |
149,467.50 |
|
Kawat beton |
kg |
0.150 |
32,100.000 |
4,815.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.070 |
94,200.000 |
6,594.00 |
|
Tukang Besi |
OH |
0.070 |
94,200.000 |
6,594.00 |
|
Kepala Tukang |
OH |
0.007 |
112,100.000 |
784.70 |
|
Mandor |
OH |
0.004 |
112,100.000 |
448.40 |
|
Jumlah harga per-10 kg satuan pekerjaan |
168,703.60 |
|
Jumlah harga per-1 kg satuan pekerjaan |
16,870.36 |
|
|
|
|
|
|
|
|
15 |
Memasang 1 m2 bekisting untuk pondasi |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Kayu kelas III (MC) |
kg |
0.040 |
3,731,000.000 |
149,240.00 |
|
Paku 5 cm - 10 cm (biasa) |
m3 |
0.300 |
18,800.000 |
5,640.00 |
|
Minyak bekisting |
m3 |
0.100 |
7,500.000 |
750.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.520 |
94,200.000 |
48,984.00 |
|
Tukang Kayu |
OH |
0.260 |
94,200.000 |
24,492.00 |
|
Kepala Tukang |
OH |
0.026 |
112,100.000 |
2,914.60 |
|
Mandor |
OH |
0.026 |
112,100.000 |
2,914.60 |
|
Jumlah harga per-satuan pekerjaan |
234,935.20 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16 |
Memasang 1 m2 bekisting untuk dinding |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Kayu kelas III (MC) |
m3 |
0.030 |
3,731,000.000 |
111,930.00 |
|
Paku 5 cm - 12 cm (biasa) |
kg |
0.400 |
18,800.000 |
7,520.00 |
|
Minyak bekisting |
liter |
0.200 |
7,500.000 |
1,500.00 |
|
Balok kayu kelas II (MC) |
m3 |
0.020 |
5,183,000.000 |
103,660.00 |
|
Dolken ky galam dia. 8 - |
btg |
3.000 |
10,000.000 |
30,000.00 |
|
10 cm, pj. 4 mtr |
|
Tenaga Kerja |
Pekerja |
OH |
0.660 |
94,200.000 |
62,172.00 |
|
Tukang Kayu |
OH |
0.330 |
94,200.000 |
31,086.00 |
|
Kepala Tukang |
OH |
0.033 |
112,100.000 |
3,699.30 |
|
Mandor |
OH |
0.033 |
112,100.000 |
3,699.30 |
|
Jumlah harga per-satuan pekerjaan |
355,266.60 |
|
|
|
|
|
|
|
|
17 |
Memasang 1 m2 bekisting untuk kolom |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Kayu kelas III (MC) |
m3 |
0.040 |
3,731,000.000 |
149,240.00 |
|
Paku 5 cm - 12 cm (biasa) |
kg |
0.400 |
18,800.000 |
7,520.00 |
|
Minyak bekisting |
liter |
0.200 |
7,500.000 |
1,500.00 |
|
Balok kayu kelas II (MC) |
m3 |
0.015 |
5,183,000.000 |
77,745.00 |
|
Dolken ky galam dia. 8 - |
btg |
2.000 |
10,000.000 |
20,000.00 |
|
10 cm, pj. 4 mtr |
|
Tenaga Kerja |
Pekerja |
OH |
0.660 |
94,200.000 |
62,172.00 |
|
Tukang Kayu |
OH |
0.330 |
94,200.000 |
31,086.00 |
|
Kepala Tukang |
OH |
0.033 |
112,100.000 |
3,699.30 |
|
Mandor |
OH |
0.033 |
112,100.000 |
3,699.30 |
|
Jumlah harga per-satuan pekerjaan |
356,661.60 |
|
|
|
|
|
|
|
|
18 |
Memasang 1 m2 bekisting untuk balok |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Kayu kelas III (MC) |
m3 |
0.040 |
3,731,000.000 |
149,240.00 |
|
Paku 5 cm - 12 cm (biasa) |
kg |
0.400 |
18,800.000 |
7,520.00 |
|
Minyak bekisting |
liter |
0.200 |
7,500.000 |
1,500.00 |
|
Balok kayu kelas II (MC) |
m3 |
0.015 |
3,731,000.000 |
55,965.00 |
|
Dolken ky galam dia. 8 - |
btg |
2.000 |
10,000.000 |
20,000.00 |
|
10 cm, pj. 4 mtr |
|
Tenaga Kerja |
Pekerja |
OH |
0.660 |
94,200.000 |
62,172.00 |
|
Tukang Kayu |
OH |
0.330 |
94,200.000 |
31,086.00 |
|
Kepala Tukang |
OH |
0.033 |
112,100.000 |
3,699.30 |
|
Mandor |
OH |
0.033 |
112,100.000 |
3,699.30 |
|
Jumlah harga per-satuan pekerjaan |
334,881.60 |
|
|
|
|
|
|
|
|
19 |
Memasang 1 m2 bekisting untuk lantai |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Kayu kelas III (MC) |
m3 |
0.040 |
3,731,000.000 |
149,240.00 |
|
Paku 5 cm - 12 cm (biasa) |
kg |
0.400 |
18,800.000 |
7,520.00 |
|
Minyak bekisting |
liter |
0.200 |
7,500.000 |
1,500.00 |
|
Balok kayu kelas II (MC) |
m3 |
0.015 |
5,183,000.000 |
77,745.00 |
|
Dolken ky galam dia. 8 - |
btg |
6.000 |
10,000.000 |
60,000.00 |
|
10 cm, pj. 4 mtr |
|
Tenaga Kerja |
Pekerja |
OH |
0.660 |
94,200.000 |
62,172.00 |
|
Tukang Kayu |
OH |
0.330 |
94,200.000 |
31,086.00 |
|
Kepala Tukang |
OH |
0.033 |
112,100.000 |
3,699.30 |
|
Mandor |
OH |
0.033 |
112,100.000 |
3,699.30 |
|
Jumlah harga per-satuan pekerjaan |
396,661.60 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
20 |
Membuat 1 m3 plat poer 100 X 100 X 20 cm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Membuat 1 m3 beton mutu K-225 |
m3 |
1.000 |
1,106,952.000 |
1,106,952.00 |
|
Pembesian 1 kg dgn besi polos atau besi ulir |
kg |
232.260 |
16,870.360 |
3,918,309.81 |
|
Memasang 1 m2 bekisting untuk pondasi |
m2 |
4.000 |
234,935.200 |
939,740.80 |
|
Jumlah harga per-satuan pekerjaan |
5,965,002.61 |
|
|
|
|
|
|
|
|
21 |
Membuat 1 m3 plat lantai IPAL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Membuat 1 m3 beton mutu K-225 |
m3 |
1.000 |
1,106,952.000 |
1,106,952.00 |
|
Pembesian 1 kg dgn besi polos atau besi ulir |
kg |
194.000 |
16,870.360 |
3,272,849.84 |
|
Memasang 1 m2 bekisting untuk pondasi |
m2 |
4.000 |
234,935.200 |
939,740.80 |
|
Jumlah harga per-satuan pekerjaan |
5,319,542.64 |
|
|
|
|
|
|
|
|
22 |
Membuat 1 m3 sloof beton 30 X 30 cm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Membuat 1 m3 beton mutu K-225 |
m3 |
1.000 |
1,106,952.000 |
1,106,952.00 |
|
Pembesian 1 kg dgn besi polos atau besi ulir |
kg |
222.800 |
16,870.360 |
3,758,716.21 |
|
Memasang 1 m2 bekisting untuk pondasi |
m2 |
6.800 |
234,935.200 |
1,597,559.36 |
|
Jumlah harga per-satuan pekerjaan |
6,463,227.57 |
|
|
|
|
|
|
|
|
23 |
Membuat 1 m3 kolom 30 X 30 cm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Membuat 1 m3 beton mutu K-225 |
m3 |
1.000 |
1,106,952.000 |
1,106,952.00 |
|
Pembesian 1 kg dgn besi polos atau besi ulir |
kg |
210.750 |
16,870.360 |
3,555,428.37 |
|
Memasang 1 m2 bekisting untuk kolom |
m2 |
13.200 |
356,661.600 |
4,707,933.12 |
|
Jumlah harga per-satuan pekerjaan |
9,370,313.49 |
|
|
|
|
|
|
|
|
24 |
Membuat 1 m3 kolom 20 X 20 cm (IPAL) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Membuat 1 m3 beton mutu K-225 |
m3 |
1.000 |
1,106,952.000 |
1,106,952.00 |
|
Pembesian 1 kg dgn besi polos atau besi ulir |
kg |
139.900 |
16,870.360 |
2,360,163.36 |
|
Memasang 1 m2 bekisting untuk kolom |
m2 |
20.000 |
356,661.600 |
7,133,232.00 |
|
Jumlah harga per-satuan pekerjaan |
10,600,347.36 |
|
|
|
|
|
|
|
|
25 |
Membuat 1 m3 balok lantai beton 30 X 30 cm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Membuat 1 m3 beton mutu K-225 |
m3 |
1.000 |
1,106,952.000 |
1,106,952.00 |
|
Pembesian 1 kg dgn besi polos atau besi ulir |
kg |
222.800 |
16,870.360 |
3,758,716.21 |
|
Memasang 1 m2 bekisting untuk balok |
m2 |
10.200 |
334,881.600 |
3,415,792.32 |
|
Jumlah harga per-satuan pekerjaan |
8,281,460.53 |
|
|
|
|
|
|
|
|
26 |
Membuat 1 m3 balok beton 20 X 20 cm (IPAL) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Membuat 1 m3 beton mutu K-225 |
m3 |
1.000 |
1,106,952.000 |
1,106,952.00 |
|
Pembesian 1 kg dgn besi polos atau besi ulir |
kg |
151.710 |
16,870.360 |
2,559,402.32 |
|
Memasang 1 m2 bekisting untuk balok |
m2 |
15.273 |
334,881.600 |
5,114,646.68 |
|
Jumlah harga per-satuan pekerjaan |
8,781,000.99 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
27 |
Membuat 1 m3 plat lantai 12 cm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Membuat 1 m3 beton mutu K-225 |
m3 |
1.000 |
1,106,952.000 |
1,106,952.00 |
|
Pembesian 1 kg dgn besi polos atau besi ulir |
kg |
148.330 |
16,870.360 |
2,502,380.50 |
|
Memasang 1 m2 bekisting untuk lantai |
m2 |
8.333 |
396,661.600 |
3,305,381.11 |
|
Jumlah harga per-satuan pekerjaan |
6,914,713.61 |
|
|
|
|
|
|
|
|
28 |
Membuat 1 m3 plat lantai 10 cm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Membuat 1 m3 beton mutu K-225 |
m3 |
1.000 |
1,106,952.000 |
1,106,952.00 |
|
Pembesian 1 kg dgn besi polos atau besi ulir |
kg |
124.000 |
16,870.360 |
2,091,924.64 |
|
Memasang 1 m2 bekisting untuk lantai |
m2 |
9.943 |
396,661.600 |
3,944,006.29 |
|
Jumlah harga per-satuan pekerjaan |
7,142,882.93 |
|
|
|
|
|
|
|
|
29 |
Memasang 1 m2 dinding bata merah tebal 1 bata, campuran spesi 1 PC : 2 PP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Bata merah |
buah |
140.000 |
1,100.000 |
154,000.00 |
|
Semen Portland |
kg |
43.500 |
1,682.000 |
73,167.00 |
|
Pasir Pasang |
m3 |
0.080 |
149,300.000 |
11,944.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.600 |
94,200.000 |
56,520.00 |
|
Tukang Batu |
OH |
0.200 |
94,200.000 |
18,840.00 |
|
Kepala Tukang |
OH |
0.020 |
112,100.000 |
2,242.00 |
|
Mandor |
OH |
0.030 |
112,100.000 |
3,363.00 |
|
Jumlah harga per-satuan pekerjaan |
320,076.00 |
|
|
|
|
|
|
|
|
30 |
Memasang 1 m2 dinding bata merah tebal 1/2 bata, campuran spesi 1 PC : 4 PP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Bata merah |
buah |
70.000 |
1,100.000 |
77,000.00 |
|
Semen Portland |
kg |
11.500 |
1,682.000 |
19,343.00 |
|
Pasir Pasang |
m3 |
0.043 |
149,300.000 |
6,419.90 |
|
Tenaga Kerja |
Pekerja |
OH |
0.300 |
94,200.000 |
28,260.00 |
|
Tukang Batu |
OH |
0.100 |
94,200.000 |
9,420.00 |
|
Kepala Tukang |
OH |
0.010 |
112,100.000 |
1,121.00 |
|
Mandor |
OH |
0.015 |
112,100.000 |
1,681.50 |
|
Jumlah harga per-satuan pekerjaan |
143,245.40 |
|
|
|
|
|
|
|
|
31 |
Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Semen Portland |
kg |
6.240 |
1,682.000 |
10,495.68 |
|
Pasir Pasang |
m3 |
0.024 |
149,300.000 |
3,583.20 |
|
Tenaga Kerja |
Pekerja |
OH |
0.200 |
94,200.000 |
18,840.00 |
|
Tukang Batu |
OH |
0.150 |
94,200.000 |
14,130.00 |
|
Kepala Tukang |
OH |
0.015 |
112,100.000 |
1,681.50 |
|
Mandor |
OH |
0.010 |
112,100.000 |
1,121.00 |
|
Jumlah harga per-satuan pekerjaan |
49,851.38 |
|
|
|
|
|
|
|
|
32 |
Memasang 1 m2 acian |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Semen Portland |
kg |
3.250 |
1,682.000 |
5,466.50 |
|
Tenaga Kerja |
Pekerja |
OH |
0.150 |
94,200.000 |
14,130.00 |
|
Tukang Batu |
OH |
0.100 |
94,200.000 |
9,420.00 |
|
Kepala Tukang |
OH |
0.010 |
112,100.000 |
1,121.00 |
|
Mandor |
OH |
0.008 |
112,100.000 |
896.80 |
|
Jumlah harga per-satuan pekerjaan |
31,034.30 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
33 |
Memasang 1 m3 kontruksi kuda-kuda konvensional |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Balok Kayu |
m3 |
1.100 |
5,183,000.000 |
5,701,300.00 |
|
Besi Strip Tebal 5 mm |
kg |
15.000 |
12,500.000 |
187,500.00 |
|
Paku 12 cm |
kg |
5.600 |
22,100.000 |
123,760.00 |
|
Tenaga Kerja |
Pekerja |
OH |
4.000 |
94,200.000 |
376,800.00 |
|
Tukang Kayu |
OH |
12.000 |
94,200.000 |
1,130,400.00 |
|
Kepala Tukang |
OH |
1.200 |
112,100.000 |
134,520.00 |
|
Mandor |
OH |
0.200 |
112,100.000 |
22,420.00 |
|
Jumlah harga per-satuan pekerjaan |
7,676,700.00 |
|
|
|
|
|
|
|
|
34 |
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas I |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Balok Kayu Ulin |
m3 |
1.100 |
11,310,000.000 |
12,441,000.00 |
|
Paku 10 cm |
kg |
1.250 |
22,100.000 |
27,625.00 |
|
Lem Kayu |
kg |
1.000 |
10,000.000 |
10,000.00 |
|
Tenaga Kerja |
Pekerja |
OH |
6.000 |
94,200.000 |
565,200.00 |
|
Tukang Kayu |
OH |
20.000 |
94,200.000 |
1,884,000.00 |
|
Kepala Tukang |
OH |
2.000 |
112,100.000 |
224,200.00 |
|
Mandor |
OH |
0.300 |
112,100.000 |
33,630.00 |
|
Jumlah harga per-satuan pekerjaan |
15,185,655.00 |
|
|
|
|
|
|
|
|
35 |
Memasang 1 m2 rangka langit-langit (60X60) cm, Kayu kelas II atau III |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Kasau (5X7) cm |
m3 |
0.016 |
5,183,000.000 |
82,928.00 |
|
Paku 7cm - 10cm |
kg |
0.250 |
18,800.000 |
4,700.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.200 |
94,200.000 |
18,840.00 |
|
Tukang Kayu |
OH |
0.300 |
94,200.000 |
28,260.00 |
|
Kepala Tukang |
OH |
0.030 |
112,100.000 |
3,363.00 |
|
Mandor |
OH |
0.010 |
112,100.000 |
1,121.00 |
|
Jumlah harga per-satuan pekerjaan |
139,212.00 |
|
|
|
|
|
|
|
|
36 |
Memasang 1 m2 langit-langit dari kalsiboard ukuran (120X240) cm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Kalsiboard tebal 3,5 mm |
lbr |
0.375 |
87,400.000 |
32,775.00 |
|
Paku 1cm - 2,5cm |
kg |
0.030 |
18,800.000 |
564.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.070 |
94,200.000 |
6,594.00 |
|
Tukang Kayu |
OH |
0.100 |
94,200.000 |
9,420.00 |
|
Kepala Tukang |
OH |
0.010 |
112,100.000 |
1,121.00 |
|
Mandor |
OH |
0.004 |
112,100.000 |
448.40 |
|
Jumlah harga per-satuan pekerjaan |
50,922.40 |
|
|
|
|
|
|
|
|
37 |
Memasang 1 m2 langit-langit kalsiboard dan rangka |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Jumlah (Rp.) |
|
a. Memasang 1 m2 rangka langit-langit (60 X 60) cm, kayu kelas II atau III |
139,212.00 |
|
b. Memasang 1 m2 langit-langit dari kalsiboard ukuran (120 X 240) cm |
50,922.40 |
|
Jumlah harga per-satuan pekerjaan |
190,134.40 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
38 |
Memasang 1 m' lisplank ukuran (2 X 2/20) cm, papan ulin |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Papan kayu ulin |
m3 |
0.011 |
22,100.000 |
243.10 |
|
Paku 5cm - 7cm |
kg |
0.050 |
22,100.000 |
1,105.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.100 |
94,200.000 |
9,420.00 |
|
Tukang Kayu |
OH |
0.200 |
94,200.000 |
18,840.00 |
|
Kepala Tukang |
OH |
0.020 |
112,100.000 |
2,242.00 |
|
Mandor |
OH |
0.005 |
112,100.000 |
560.50 |
|
Jumlah harga per-satuan pekerjaan |
32,410.60 |
|
|
|
|
|
|
|
|
39 |
Memasang 1 m' lisplank ukuran (2 X 2/20) cm, papan MC |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Papan kayuMC |
m3 |
0.011 |
3,731,000.000 |
41,041.00 |
|
Paku 5cm - 7cm |
kg |
0.050 |
18,800.000 |
940.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.100 |
94,200.000 |
9,420.00 |
|
Tukang Kayu |
OH |
0.200 |
94,200.000 |
18,840.00 |
|
Kepala Tukang |
OH |
0.020 |
112,100.000 |
2,242.00 |
|
Mandor |
OH |
0.005 |
112,100.000 |
560.50 |
|
Jumlah harga per-satuan pekerjaan |
73,043.50 |
|
|
|
|
|
|
|
|
40 |
Memasang 1 m2 lantai keramik ukuran ( 30 X 30 ) cm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Keramik |
m2 |
1.000 |
65,300.000 |
65,300.00 |
|
Semen Portland |
kg |
10.000 |
1,682.000 |
16,820.00 |
|
Pasir Pasang |
m3 |
0.045 |
149,300.000 |
6,718.50 |
|
Semen Warna |
kg |
1.500 |
15,000.000 |
22,500.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.620 |
94,200.000 |
58,404.00 |
|
Tukang Batu |
OH |
0.350 |
94,200.000 |
32,970.00 |
|
Kepala Tukang |
OH |
0.035 |
112,100.000 |
3,923.50 |
|
Mandor |
OH |
0.030 |
112,100.000 |
3,363.00 |
|
Jumlah harga per-satuan pekerjaan |
209,999.00 |
|
|
|
|
|
|
|
|
41 |
Memasang 1 m2 lantai keramik ukuran (20X20) cm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Keramik |
m2 |
1.000 |
65,300.000 |
65,300.00 |
|
Semen Portland |
kg |
10.400 |
1,682.000 |
17,492.80 |
|
Pasir Pasang |
m3 |
0.045 |
149,300.000 |
6,718.50 |
|
Semen Warna |
kg |
1.620 |
15,000.000 |
24,300.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.620 |
94,200.000 |
58,404.00 |
|
Tukang Batu |
OH |
0.350 |
94,200.000 |
32,970.00 |
|
Kepala Tukang |
OH |
0.035 |
112,100.000 |
3,923.50 |
|
Mandor |
OH |
0.030 |
112,100.000 |
3,363.00 |
|
Jumlah harga per-satuan pekerjaan |
212,471.80 |
|
|
|
|
|
|
|
|
42 |
Memasang 1 m2 dinding keramik ukuran (20 X 20) cm |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Keramik |
m2 |
1.000 |
65,300.000 |
65,300.00 |
|
Semen Portland |
kg |
9.300 |
65,300.000 |
607,290.00 |
|
Pasir Pasang |
m3 |
0.018 |
3,731,000.000 |
67,158.00 |
|
Semen Warna |
kg |
1.940 |
15,000.000 |
29,100.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.600 |
94,200.000 |
56,520.00 |
|
Tukang Batu |
OH |
0.450 |
94,200.000 |
42,390.00 |
|
Kepala Tukang |
OH |
0.0450 |
112,100.000 |
5,044.50 |
|
Mandor |
OH |
0.0300 |
112,100.000 |
3,363.00 |
|
Jumlah harga per-satuan pekerjaan |
876,165.50 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
43 |
Memasang 1 m2 atap genteng metal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Atap genteng metal |
m2 |
1.020 |
64,800.000 |
66,096.00 |
|
Paku atap |
kg |
0.200 |
32,100.000 |
6,420.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.200 |
94,200.000 |
18,840.00 |
|
Tukang Kayu |
OH |
0.100 |
94,200.000 |
9,420.00 |
|
Kepala Tukang |
OH |
0.0100 |
112,100.000 |
1,121.00 |
|
Mandor |
OH |
0.0100 |
112,100.000 |
1,121.00 |
|
Jumlah harga per-satuan pekerjaan |
103,018.00 |
|
|
|
|
|
|
|
|
44 |
Pengecatan 1 m2 bidang kayu baru, 1 lapis cet dasar 2 lapis cat penutup |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Cat Menei |
kg |
0.200 |
25,400.000 |
5,080.00 |
|
Plamir |
kg |
0.150 |
15,000.000 |
2,250.00 |
|
Cet Dasar |
kg |
0.170 |
25,400.000 |
4,318.00 |
|
Cat Penutup 2X |
kg |
0.260 |
22,120.000 |
5,751.20 |
|
Tenaga Kerja |
Pekerja |
OH |
0.070 |
94,200.000 |
6,594.00 |
|
Tukang Cat |
OH |
0.090 |
94,200.000 |
8,478.00 |
|
Kepala Tukang |
OH |
0.006 |
112,100.000 |
672.60 |
|
Mandor |
OH |
0.003 |
112,100.000 |
280.25 |
|
Jumlah harga per-satuan pekerjaan |
33,424.05 |
|
|
|
|
|
|
|
|
45 |
Pengecatan 1 m2 bidang tembok baru, 1 lapis plamir 1 lapis cat dasar 2 lapis cat penutup |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Plamir |
kg |
0.100 |
15,000.000 |
1,500.00 |
|
Cat Dasar |
kg |
0.100 |
25,400.000 |
2,540.00 |
|
Cat Penutup 2X |
kg |
0.260 |
22,120.000 |
5,751.20 |
|
Tenaga Kerja |
Pekerja |
OH |
0.020 |
94,200.000 |
1,884.00 |
|
Tukang Cat |
OH |
0.063 |
94,200.000 |
5,934.60 |
|
Kepala Tukang |
OH |
0.0063 |
112,100.000 |
706.23 |
|
Mandor |
OH |
0.0025 |
112,100.000 |
280.25 |
|
Jumlah harga per-satuan pekerjaan |
18,596.28 |
|
|
|
|
|
|
|
|
46 |
Pekerjaan 1 kg, besi + pengelasan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kebutuhan |
Satuan |
Indeks |
Harga (Rp.) |
Jumlah (Rp.) |
|
Bahan |
Pipa GI |
kg |
1.100 |
20,000.000 |
22,000.00 |
|
Cat Menei |
kg |
0.080 |
25,400.000 |
2,032.00 |
|
Cat Kilap Penutup 2X |
kg |
0.080 |
50,900.000 |
4,072.00 |
|
Tenaga Kerja |
Pekerja |
OH |
0.060 |
94,200.000 |
5,652.00 |
|
Tukang Besi |
OH |
0.006 |
94,200.000 |
565.20 |
|
Kepala Tukang |
OH |
0.0060 |
112,100.000 |
672.60 |
|
Mandor |
OH |
0.0003 |
112,100.000 |
33.63 |
|
Jumlah harga per-satuan pekerjaan |
35,027.43 |