Sheet 1: RAB
Rencana Anggaran Biaya (RAB) | |||||||
Proyek : Rumah 1 Unit | |||||||
Lokasi : Batam | |||||||
NO. | URAIAN PEKERJAAN | SATUAN | VOLUME | HARGA SAT. | JUMLAH HARGA | BOBOT | |
[SAT.] | [VOL.] | [Rp.] | [Rp.] | [%] | |||
A | PEKERJAAN PENDAHULUAN | ||||||
1 | Pek. Pengukuran / Pas. Bouwplank | m1 | 18.00 | 91,760 | 1,651,680 | ||
2 | Pek. Penyediaan Air Kerja | Ls | 1.00 | 5,000,000 | 5,000,000 | ||
3 | Penyediaan Gudang / Direksi Keet / Pagar Proyek | Ls | 1.00 | 20,000,000 | 20,000,000 | ||
SUB-TOTAL [Rp.] | 26,651,680 | ||||||
B | PEKERJAAN PONDASI | ||||||
1 | Pek. Galian Pondasi Setempat (PS) | M3 | 50.70 | 46,200 | 2,342,340 | ||
2 | Pek. Galian Sloof S1 20/40 | M3 | 16.72 | 46,200 | 772,464 | ||
3 | Pek. Urugan Pasir dibawah PS | M3 | 1.95 | 128,700 | 250,965 | ||
4 | Pek. Cor Tapak Pondasi 30x120x130 | M3 | 11.70 | 3,671,350 | 42,954,795 | ||
5 | Pek. Stik Kolom 20/40 | M3 | 2.00 | 3,671,350 | 7,342,700 | ||
SUB-TOTAL [Rp.] | 53,663,264 | ||||||
C | PEKERJAAN STRUKTUR | ||||||
1 | Pek. Sloof S1 20/40 | M3 | 16.72 | dst… | dst… | ||
2 | Pek. Kolom K1 15/40 | M3 | 6.00 | dst… | dst… | ||
3 | Pek. Kolom Praktis K2 15/15 | M3 | 2.88 | dst… | dst… | ||
4 | Pek. Balok Gantung Pintu Depan 15/25 | M3 | 0.23 | dst… | dst… | ||
5 | Pek. Plat Beton Pintu Depan, tebal 10cm | M3 | 0.74 | dst… | dst… | ||
6 | Pek. Cor Rabat Lantai | M3 | 16.80 | dst… | dst… | ||
SUB-TOTAL [Rp.] | dst… | ||||||
D | PEKERJAAN DINDING BATA | ||||||
1 | Pek. Pas. Dinding 1/2 Bata Camp. 1:4 | M2 | 706.67 | dst… | dst… | ||
2 | Pek. Plesteran dan Aci 1:4 | M2 | 1,413.34 | dst… | dst… | ||
SUB-TOTAL [Rp.] | dst… | ||||||
E | PEK. KUSEN, PINTU, JENDELA, DAN AKSESORIS | ||||||
1 | Pek. Kusen & Pintu Utama (Pintu 2 Daun) | Unit | 4.00 | dst… | dst… | ||
2 | Pek. Kusen & Pintu Belakang (Pakai Jalusi Kayu) | Unit | 4.00 | dst… | dst… | ||
3 | Pek. Kusen & Pintu K.Tidur | Unit | 8.00 | dst… | dst… | ||
4 | Pek. Pintu Fiber Sisir KM [tanpa kozen] | Unit | 4.00 | dst… | dst… | ||
5 | Pek. Kusen & Daun Jendela Kaca Depan | Unit | 4.00 | dst… | dst… | ||
6 | Pek. Kusen & Jendela Kaca Nako Belakang (Pakai Jalusi Kayu) | Unit | 4.00 | dst… | dst… | ||
SUB-TOTAL [Rp.] | dst… | ||||||
F | PEKERJAAN INSTALASI LISTRIK | ||||||
1 | Pek. Instalasi Titik Lampu & Stop Kontak | Ttk | 64.00 | dst… | dst… | ||
2 | Pek. Pas. Saklar | Bh | 36.00 | dst… | dst… | ||
3 | Pek. Pas. Stop Kontak | Set | 28.00 | dst… | dst… | ||
4 | Pek. Panel box | Unt | 4.00 | dst… | dst… | ||
SUB-TOTAL [Rp.] | dst… | ||||||
G | PEKERJAAN SANITAIR | ||||||
1 | Pek. Instalasi Air Bersih [Pipa PVC 3/4" dan 1/2"] | M' | 104.00 | dst… | dst… | ||
2 | Pek. Instalasi Air Kotor K.Mandi, Dapur, Air Hujan [Pipa PVC Ø3"] | M' | 154.00 | dst… | dst… | ||
3 | Pek. Instalasi Air Buangan Closet [Pipa PVC Ø4"] | M' | 48.00 | dst… | dst… | ||
4 | Pek. Septick tank | Unt | 4.00 | dst… | dst… | ||
SUB-TOTAL [Rp.] | dst… | ||||||
H | PEKERJAAN ATAP BETON | ||||||
1 | Pek. Balok Gantung 25/50 | M3 | 10.00 | dst… | dst… | ||
2 | Pek. Balok Duduk 20/40 | M3 | 6.00 | dst… | dst… | ||
3 | Pek. Cor Plat Beton (tbl. 10 cm) | M3 | 24.00 | dst… | dst… | ||
4 | Pek. Kolom Praktis K2 15/15 (Pagar Keliling Atap) | M3 | 0.56 | dst… | dst… | ||
5 | Pek. Pas. Dinding 1/2 Bata Camp. 1:4 | M2 | 85.60 | dst… | dst… | ||
6 | Pek. Plesteran dan Aci Bata 1:4 | M2 | 214.00 | dst… | dst… | ||
7 | Pek. Plesteran dan Aci Lantai Atap 1:4 | M2 | 240.00 | dst… | dst… | ||
8 | Pek. Floor Drain | M2 | 12.00 | dst… | dst… | ||
SUB-TOTAL [Rp.] | dst… | ||||||
I | PEKERJAAN FINISHING | ||||||
1 | Pek. Keramik Lantai (Keramik 40x40) | M2 | 240.00 | dst… | dst… | ||
2 | Pek. Keramik K.Mandi | Unit | 4.00 | dst… | dst… | ||
3 | Pek. Meja Dapur dan Pas. Keramik | Unit | 4.00 | dst… | dst… | ||
4 | Pek. Plafon | M2 | 240.00 | dst… | dst… | ||
5 | Pek. Finishing Plesteran Motif Tpk. Depan | Unit | 4.00 | dst… | dst… | ||
6 | Pek. Cat Dinding Luar | M2 | 500.60 | dst… | dst… | ||
7 | Pek. Cat Dinding Dalam dan Plafon | M2 | 1147.20 | dst… | dst… | ||
8 | Pek. Cat Kusen, Daun Pintu, dan Daun Jendela | Unit | 28.00 | dst… | dst… | ||
SUB-TOTAL [Rp.] | dst… | ||||||
TOTAL [Rp.] | 80,314,944 | 0.00 | |||||
Indonesia, 7 Juli 2017 | |||||||
Dibuat Oleh: | |||||||
Rahmad Khairul |
Daftar Harga Bahan dan Upah | |||
Proyek : Rumah 1 Unit | |||
Lokasi : Batam | |||
A. | Harga Bahan (Material) | ||
No. | Nama Bahan (Material) | Satuan | Harga Satuan (Rp.) |
1 | Kayu gergajian kelas III, papan | m3 | 4,800,000 |
2 | Kayu gergajian kelas III, balok | m3 | 4,800,000 |
3 | Paku berbagai ukuran (2" - 5") | kg | 13,000 |
4 | Pasir urug / timbun | m3 | 90,000 |
5 | Minyak bekisting | ltr | 5,000 |
6 | Besi beton | kg | 8,500 |
7 | Kawat beton | kg | 18,000 |
8 | Semen PC @ 50 kg | kg | 1,200 |
9 | Pasir ayak untuk beton | m3 | 100,000 |
10 | Batu pecah 2 - 3 (cm) | m3 | 265,000 |
B. | Harga Upah | ||
No. | Uraian | Satuan | Harga Satuan (Rp.) |
1 | Mandor | m3 | 120,000 |
2 | Kepala tukang | m3 | 100,000 |
3 | Tukang batu | kg | 90,000 |
4 | Tukang kayu | m3 | 90,000 |
5 | Tukang besi / tukang las | ltr | 90,000 |
6 | Pekerja tak terlatih | kg | 65,000 |
Analisa Harga Satuan Bahan dan Upah | ||||||||
Proyek : Rumah 1 Unit | ||||||||
Lokasi : Batam | ||||||||
Kode Analisa | Uraian Pekerjaan | Harga Satuan (Rp.) | Harga Analisa (Rp.) | Harga Analisa | ||||
Bahan | Upah | Bahan | Upah | Bahan dan Upah (Rp.) | ||||
A.4 | 1 m' Pengukuran dan pemasangan bouwplank, papan 2/10 | |||||||
0.0035 | m³ | Kayu gergajian kelas III, papan | 4,800,000.00 | 16,800.00 | ||||
0.0120 | m³ | Kayu gergajian kelas III, balok | 4,800,000.00 | 57,600.00 | ||||
0.0200 | kg | Paku berbagai ukuran (2" - 5") | 13,000.00 | 260.00 | ||||
0.1000 | Oh | Pekerja tak terlatih | 65,000.00 | 6,500.00 | ||||
0.1000 | Oh | Tukang kayu | 90,000.00 | 9,000.00 | ||||
0.0100 | Oh | Kepala tukang | 100,000.00 | 1,000.00 | ||||
0.0050 | Oh | Mandor | 120,000.00 | 600.00 | ||||
Jumlah (Rp.) | 74,660.00 | 17,100.00 | 91,760.00 | |||||
B.1 | 1 m³ Galian Tanah biasa Sedalam 1 m (dengan tenaga) | |||||||
0.6000 | Oh | Pekerja tak terlatih | 65,000.00 | 39,000.00 | ||||
0.0600 | Oh | Mandor | 120,000.00 | 7,200.00 | ||||
Jumlah (Rp.) | - | 46,200.00 | 46,200.00 | |||||
B.11 | 1 m³ Urugan Pasir (dengan tenaga) | |||||||
1.2000 | m³ | Pasir urug / timbun | 90,000.00 | 108,000.00 | ||||
0.3000 | Oh | Pekerja tak terlatih | 65,000.00 | 19,500.00 | ||||
0.0100 | Oh | Mandor | 120,000.00 | 1,200.00 | ||||
Jumlah (Rp.) | 108,000.00 | 20,700.00 | 128,700.00 | |||||
G.29 | 1 m³ Membuat pondasi beton bertulang (150 kg besi + bekisting) | |||||||
0.2000 | m³ | Kayu gergajian kelas IV, papan | 4,800,000.00 | 960,000.00 | ||||
1.5000 | kg | Paku berbagai ukuran (2" - 5") | 13,000.00 | 19,500.00 | ||||
0.4000 | ltr | Minyak bekisting | 5,000.00 | 2,000.00 | ||||
157.5000 | kg | Besi beton | 8,500.00 | 1,338,750.00 | ||||
2.2500 | kg | Kawat beton | 18,000.00 | 40,500.00 | ||||
336.0000 | kg | Semen PC @ 50 kg | 1,200.00 | 403,200.00 | ||||
0.5400 | m³ | Pasir ayak untuk beton | 100,000.00 | 54,000.00 | ||||
0.8100 | m³ | Batu pecah 2 - 3 (cm) | 265,000.00 | 214,650.00 | ||||
5.3000 | Oh | Pekerja tak terlatih | 65,000.00 | 344,500.00 | ||||
0.2750 | Oh | Tukang batu | 90,000.00 | 24,750.00 | ||||
1.3000 | Oh | Tukang kayu | 90,000.00 | 117,000.00 | ||||
1.0500 | Oh | Tukang besi / tukang las | 90,000.00 | 94,500.00 | ||||
0.2620 | Oh | Kepala tukang | 100,000.00 | 26,200.00 | ||||
0.2650 | Oh | Mandor | 120,000.00 | 31,800.00 | ||||
Jumlah (Rp.) | 3,032,600.00 | 638,750.00 | 3,671,350.00 | |||||
`` |